The Bandar Lawas Bridge is a 642-metre road crossing of the Sungai Lawas that joins the northern and southern halves of Lawas town. Bernama put the project's value at RM149 million, and the Sarawak Public Communications Unit (UKAS) reported that it opened to the public on 6 November 2026.

Lawas is the northernmost district of Sarawak and sits in the Limbang division, between Brunei and Sabah. Until the bridge, the town was split by its own river.

What the bridge replaces

Before the crossing existed, people going from one bank to the other had two choices, according to Bernama's report from Lawas in July 2026:

  • a river boat, which a resident of Kampung Belimbing told the agency costs RM1 each way; or
  • a much longer route by road.

A resident of Kampung Seberang Kedai told Bernama the boats usually stop at about 6pm, so an emergency at night meant taking the long way round. The same report said the bridge is expected to cut the journey from about 50 minutes to about 25, and that it will serve as a main route between Merapok and Lawas town.

Who built it, and under which agency

The bridge is a project of the Northern Region Development Agency (NRDA), which is supervised by the Regional Corridor Development Authority (RECODA). UKAS described it in August 2025 as one of NRDA's major development initiatives. NRDA is chaired by Deputy Premier Datuk Amar Awang Tengah Ali Hasan.

Bernama reported that the design carries eight decorative domes on four towers, and that the concept came from Awang Tengah, who is also the assemblyman for Bukit Sari, after he studied well-known bridges abroad. RECODA's chief executive, Datuk Ismawi Ismuni, told UKAS the finished bridge can take vehicles of all types, heavy vehicles included, and has its own lighting system.

How long it took

The official releases trace the work over two years:

  1. November 2024: RECODA reported the launch of a bridge girder during an NRDA site visit.
  2. August 2025: physical progress stood at 62.6 per cent when Awang Tengah inspected the site, with completion expected in the fourth quarter of 2026.
  3. June 2026: progress reached 97 per cent, ahead of schedule. The remaining work was architectural: the domes, the main gateway and the lighting.
  4. 15 October 2026: the bridge received its Certificate of Practical Completion and passed a road safety audit, Ismawi said.
  5. 6 November 2026: it opened to traffic.

UKAS said on 6 November that the bridge would close again from 10 to 22 November to prepare for an official opening ceremony, scheduled for 18 November with the Premier officiating and about 1,500 guests expected, and would reopen to the public afterwards.

Why the south bank matters

The bridge is meant to open land as well as shorten a journey. NRDA's regional director, Datuk Ubaidillah Abdul Latip, told Bernama the south bank has been set aside for future redevelopment and expansion of the town, which the state government is planning. Ismawi said the crossing would support housing, commercial and industrial development there.

Where it fits in the northern plan

Bernama reported that the bridge is part of RECODA's plan to make Lawas the northern gateway of Sarawak, under the Trusan, Sundar and Merapok Action Area Plan. Other pieces of that plan are at different stages:

Awang Tengah said on 18 November that Limbang and Lawas, which border Brunei, Sabah and Kalimantan, could become a cross-border economic corridor, and that several bridge projects in the two districts are being paid for from state funds.