Lawas is getting a new water treatment plant at Lakutan that will produce 20 million litres a day to begin with, at a cost of RM160.69 million paid entirely by the Sarawak Government. It is scheduled for completion on 8 December 2028, according to the state's information unit, UKAS.
Deputy Premier Datuk Amar Awang Tengah Ali Hasan performed the groundbreaking for the Pengalih Lakutan Water Treatment Plant on Tuesday, 17 November. The plant is being built by the Rural Water Supply Department (JBALB) Sarawak. It sits in the Limbang division, where treated water reaches fewer households than the Sarawak average.
What RM160.69 million is buying
The UKAS report of the ceremony lists the scope of the project:
- a treatment plant with an initial output of 20 million litres a day, which can be raised to 60 million litres a day when demand calls for it
- a raw water intake sized at 60 million litres a day from the start
- a high-level water tank and storage
- main pipelines, and connections that run as far as residents' homes
Awang Tengah told reporters the distribution works were included so that the extra production turns into supply that actually reaches people, rural communities in particular.
Which parts of Lawas the plant will serve
The new plant is meant to work alongside the existing supply from Trusan, with the two networks supporting each other. Awang Tengah named Lawas Damit, the villages along that route and the Merapok area as the places it is intended to supply, UKAS reported. He said the system would extend coverage to areas that had been hard to connect because of the terrain and road access.
Places that still cannot be joined to the main pipes are to be supplied by stand-alone systems, including the Sarawak Alternative Water Supply programme, known as SAWAS.
Why the ceremony came five months after work began
The official account says construction work started on 8 June 2026, so the groundbreaking on 17 November was a formal occasion and not the first day on site. Utilities and Telecommunications Minister Dato Sri Julaihi Narawi, speaking at the same ceremony, put physical progress at 1.34 per cent, according to a second UKAS report.
Two details differ between the official accounts and are worth noting:
- The cost is RM160.69 million in the report of the Deputy Premier's remarks and RM160.68 million in the report of the minister's speech.
- When the plant was first announced in March 2025, Bernama reported Awang Tengah as saying it would be built at Sungai Lawas Damit and was expected to start that year. He said then that it would benefit residents from Long Tuma to SMK Merapok and open the way to extending coverage to Kampung Long Sukang. This week's reports give the site as Lakutan and the start as June 2026.
Where Lawas stands on treated water today
Julaihi said treated water coverage is 76 per cent in Lawas district and 75 per cent in Limbang district, against 86.1 per cent for Sarawak as a whole, UKAS reported.
The state has allocated RM717.27 million for 27 water supply projects in the Limbang division. The minister said 22 of them, or 81.5 per cent, are complete. Among the finished work is the upgrading of the Berawan plant in Limbang, which doubled its capacity from 20 to 40 million litres a day.
In Lawas district two plants are now under construction: the Lakutan plant and a new Trusan plant of 50 million litres a day. Julaihi said the two would become the main plants in the district's supply system once finished, in line with the state's water supply master plan and water grid. Trusan was described as the district's main source of water in the Bernama report of March 2025.
What else is being replaced in the division
A plant adds little if the pipes downstream leak. The minister said 14 projects worth RM80.8 million are replacing 119.8km of old and worn water pipes in the Limbang division in phases, with completion expected by 2029, according to UKAS. That is part of a statewide programme covering 2,740km of pipe at a cost of RM1.1 billion, aimed at cutting non-revenue water.
He also described the Sarawak water supply grid now being developed, which takes in 32 main treatment plants and 2,934km of pipeline so that connected areas can share water. Julaihi said the ministry and JBALB would tighten monitoring and coordination so that projects finish on schedule.