A government building project in Sarawak that falls far enough behind is labelled a "sick" project, and the contractor then faces one of two penalties: daily damages for lateness, or the loss of the contract. Four rural school projects are at that stage now. On 18 November 2026 the federal Deputy Works Minister, Datuk Seri Ahmad Maslan, said three school contractors had been fined and a fourth had been sent a termination notice, Bernama reported in its Malay-language service.
The four schools show both penalties at work
The projects named by the deputy minister are SMK Tinjar in Baram, SK Sebat in Lundu, SMK Belaga and SK Abang Leman in Saratok. Each is between 18 and 33 per cent behind schedule, according to Bernama's report of his press conference in Kuching.
- SK Abang Leman, Saratok: a notice to terminate the contract was issued on 10 November. The job covers the full replacement of 30 classrooms, a hostel for 600 pupils and 12 teachers' quarters.
- SMK Belaga, SK Sebat and SMK Tinjar: the contractors have had liquidated and ascertained damages (LAD) imposed, the contractual fine for late delivery.
SK Sebat is in Lundu, part of the Kuching division.
How long a project can stall before the department may act
The threshold has been a point of argument. In March 2025 Sarawak's Infrastructure and Port Development Minister, Datuk Amar Douglas Uggah Embas, said the Public Works Department (JKR) rule then in force allowed action only when an approved project had not been actively carried out for 100 days. His ministry was looking at cutting that to 30 days, he told Bernama, so that JKR could intervene and decide on termination earlier. The sources read for this article do not say whether the shorter period was adopted.
A separate condition applies at the start of a job. In January 2023 Uggah said contractors awarded Sarawak government projects must begin work within one month of receiving the contract or face action that could include termination. He gave two reasons: some contractors were holding 20 or more projects at once, and repeated subcontracting was affecting quality.
What happens after a contractor is removed
Termination does not finish the building. The remaining work is re-let to what JKR calls a rescue contractor, and the clock starts again. The Sebauh Bridge in Bintulu is the documented example. The 728.56-metre crossing of the Kemena River, costing RM74,893,670, was at one point three years late. The first contractor was removed with 50.61 per cent of the work done, and a rescue contractor was given 24 months to complete the rest, according to a ministry report published before the bridge's December 2025 deadline. At that visit the bridge was 3.64 per cent ahead of the new schedule.
Before termination there is usually a final warning. At the RM385 million Batang Saribas 2 bridge in Pusa, Betong, which was 34 days late even after an extension of time, JKR gave the contractor two weeks to fix shortages of workers and machinery, the ministry reported in a notice dated 1 July. Uggah said the termination process would follow if the problems were not resolved.
Federal ministries wait for JKR Sarawak's assessment
Many federal buildings in Sarawak are built for a client ministry with JKR Sarawak supervising. On 16 November 2026 the Deputy Communications Minister, Teo Nie Ching, said two projects held by one contractor were two and four months late: RTM staff quarters in Sri Aman, worth more than RM9.98 million, and an additional Information Department building worth more than RM19.77 million. Her ministry would wait for JKR Sarawak's professional assessment before deciding whether the contractor continues, Bernama reported.
Not every delay counts against the contractor. In the same report, RTM quarters in Sibu received a 45-day extension of time because of ground conditions, moving completion to 17 September 2027.
How many projects are sick
The numbers come from different governments and different years, so they do not add up to one total.
- Nationally: 880 projects worth RM51.75 billion are under construction with JKR monitoring. Of those, 272 are ahead of schedule, 311 are on schedule and 26 are sick, or 2.97 per cent, down from 38.
- State projects: in March 2025 Uggah said Sarawak's own count had fallen from more than 100 to two since he took the portfolio. That figure is now 20 months old.
More school work is coming. Ahmad Maslan said 18 Sarawak projects costing an estimated RM1.14 billion are listed for 2027 under the Thirteenth Malaysia Plan's second rolling plan, and 14 of them belong to the Ministry of Education.
Sources
- BERNAMA - Kontraktor Empat Projek Sekolah Luar Bandar Sarawak Dikenakan Denda, Notis Penamatan — Bernama
- BERNAMA - Sarawak Mulls Shortening Duration To Classify Sick Projects -- Uggah — Bernama
- CONTRACTORS WHO FAIL TO START WORK ON GOVT PROJECTS IN S'WAK WITHIN A MONTH CAN BE FIRED - DOUGLAS UGGAH - BERNAMA — Bernama
- News - Ministry of Infrastructure and Port Development Sarawak — Sarawak Government
- News - Ministry of Infrastructure and Port Development Sarawak — Sarawak Government
- BERNAMA - JKR Sarawak To Assess Contractor's Performance Over Two Delayed Projects – Teo — Bernama