Kapit town's congestion followed the completion of the road from Sibu in October 2021, on the Sarawak Premier's own account. The state government's main answer so far is RM190 million for road widening and smart traffic lights in the town, approved in June 2022. Around that sit a second road link to Sibu, a bridge over the Rajang and a plan to make the town easier to walk.
This is a guide to what has been announced for Kapit, by whom, and when. The figures come from Bernama reports between 2022 and 2025 and each is dated below, because several are now some years old.
Why a town on the Rajang filled with cars
Works Minister Datuk Seri Alexander Nanta Linggi, who is also the Kapit MP, said in May 2024 that the existing Sibu-Kapit road was completed in October 2021 and that express boat operations stopped afterwards, Bernama reported.
Eight months after the road opened, Premier Tan Sri Abang Johari Tun Openg said Kapit town was experiencing congestion because the number of vehicles had risen since the link to Sibu was finished, according to Bernama's report of 6 June 2022.
What the RM348 million of June 2022 was for
On that visit the Premier announced RM348 million for road and electricity works in the Kapit division. Bernama's report breaks it down:
- RM190 million to widen roads and install smart traffic lights in Kapit town
- RM105 million for a road connecting Sungai Katibas with Ulu Sungai Bangkit in Song district
- RM53 million to bring Kapit electricity from the state grid, from Sungai Tunoh
He said two state ministries, the one responsible for local government and the transport ministry, had been directed to go to Kapit to carry out further surveys. The reports we have read do not say how much of the town road work has since been finished.
How big the wider building programme is
The town works are a small part of what is being spent in the division. In February 2023 Abang Johari said the state had spent RM400 million in Kapit division over the previous three years through the Upper Rajang Development Agency (URDA) and other state projects, Bernama reported. He said some projects were delayed by logistics, and that barges on the river could carry building materials more cheaply than lorries on the road.
He also said then that there was a master plan to expand Kapit with a new urban area, connected to the main road to Sibu, covering a commercial centre, housing and roads.
By June 2025 the count under the state infrastructure ministry alone was 40 projects worth RM1.233 billion, Deputy Premier Datuk Amar Douglas Uggah Embas said, according to Bernama:
- 19 projects completed
- five under way, costing RM116 million, for roads and bridges
- 16, worth RM721 million, expected to go to tender that year
Which new links would take pressure off the one road in
Two federally backed projects would give Kapit more than the one existing road to Sibu.
- A second Sibu-Kapit route. Nanta said in May 2024 that a new road of about 66km would be built in three phases from the Nanga Kabah area to the bank opposite Kapit town, with a bridge across the Rajang between Song and Kapit. Phase 1 is 16.35km, costs RM145.89 million and is scheduled for completion by 31 March 2027, Bernama reported.
- Nanga Semaram to Kapit. Prime Minister Datuk Seri Anwar Ibrahim said in September 2024 that a 72km road from Nanga Semaram in Kanowit to Kapit was a federal priority, with the first phase to start by the end of 2025 or in 2026. He also described a project at Nanga Yong of a new road and two bridges linking Jalan Ng Belawai to Jalan Song-Kapit, due to run from 2025 to 2029, Bernama reported.
What kind of town the state says it is aiming for
In November 2025 Abang Johari said Kapit would become a modern inland town within five to 10 years. He said he wanted it to be pedestrian-friendly and built around eco-tourism, on the advice of planning experts from Norway, Bernama reported.
At the same event he said RM1.96 billion had been approved to supply Kapit with treated water, and announced the RM122 million Jalan Merirai project and a 7km Jalan Tunoh to connect resettlement areas. The reports do not say how the pedestrian-friendly aim fits with the road widening funded in 2022.
Sources
- BERNAMA - Sarawak Premier injects RM348 million to develop Kapit — Bernama
- BERNAMA - Kapit development: RM400 million spent over last three years - Abang Johari — Bernama
- BERNAMA - New Road Will Be Constructed To Link Sibu, Kapit Divisions - Nanta — Bernama
- BERNAMA - Federal Govt To Give Priority To Road Building In Kapit - Anwar — Bernama
- BERNAMA - 40 Infrastructure Projects For Kapit - Deputy Premier — Bernama
- BERNAMA - Kapit Set To Become Modern Inland Town Within 10 Years - Sarawak Premier — Bernama